Net metering in the Philippines: how it works, who qualifies and what it changes
The short answer: net metering lets a house with solar panels send its surplus into the utility’s lines and get a credit on the bill for it. The program has run since 2013, and its rules were amended in 2019, 2024, 2025 and 2026.
By Hamza Rivera, updated
Short answer: Net metering lets a house with solar panels send its surplus into the utility's lines and get a credit on the bill. It covers systems up to 100 kilowatts, needs a bi-directional meter, and has run since 2013 under Energy Regulatory Commission rules that changed in 2019, 2024, 2025 and 2026.
This page is the current version, with the source and date beside each rule. The forms themselves come from whichever utility bills you, and what each utility around Pampanga publishes is a page of its own. How net metering shows up on your bill is in understanding net metering and your electric bill.
What net metering is
The Department of Energy’s primer puts it in one paragraph. A customer of a distribution utility installs a renewable energy system of up to 100 kilowatts on their own premises and uses the electricity it makes. Anything the house is not using at that moment goes out through the meter into the utility’s system, and the utility credits it against the bill. The DOE calls such a customer a prosumer, because they both produce and consume.
Two meters matter. Most houses have a meter that counts in one direction only. Net metering needs a bi-directional meter, which records what comes in from the grid and what goes out to it as two separate figures. Meralco’s FAQ is blunt about what happens without one: a one-way meter can record your exported solar as imported power and raise the bill. How to read a meter that counts both ways shows where the two readings sit.
Who is eligible
The national conditions are short. You are a customer of a distribution utility or an electric cooperative, your account is in good credit standing, and the system is up to 100 kilowatts, which for solar Meralco reads as 100 kilowatts-peak. Meralco’s own list adds that the account must be registered in the applicant’s name and carry no unsettled bill when you apply. A cooperative may word its conditions differently, and the only way to know is to ask the one whose name is on your statement.
Nothing in the rules requires you to own the roof, but the account and the agreement are in the applicant’s name, so a tenant needs the account holder on side. Since August 2025 a credit balance can follow the property to a new owner, with a conforme letter from the old one.
The rules, in date order
Each row names the instrument and the document it was read from. Anything written about net metering before the row it contradicts is out of date on that point.
- 2008 Republic Act 9513, the Renewable Energy Act
- Introduced net metering in Philippine law and set the ceiling: a renewable energy system of up to 100 kilowatts on the customer’s own premises.
- Source: DOE net metering primer, September 2022.
- 24 July 2013 ERC Resolution No. 09, Series of 2013
- The Rules Enabling the Net-Metering Program for Renewable Energy. Adopted on 27 May 2013, published on 10 July 2013 and in effect fifteen days later. This is the rulebook every utility has run the program under since.
- Source: DOE net metering primer, September 2022.
- 2019 ERC Resolution No. 06, Series of 2019
- Amended the 2013 rules. Export credits are valued at the distribution utility’s blended generation cost, excluding other generation adjustments, which is less than the full rate you pay per kilowatt-hour.
- Source: DOE net metering primer, September 2022.
- 19 August 2024 DOE Department Circular DC2024-08-0025
- Removed the one calendar year limit on banked credits, so unused credits no longer lapse at year end, and removed the rule that limited generation to the household’s own annual consumption.
- Source: Cruz Marcelo and Tenefrancia client note on the circular.
- 27 August 2025 ERC Resolution No. 15, Series of 2025
- The 2025 Amended Rules. Credits bank and roll over against current and future bills, and may pass to a new owner of the property with a conforme letter from the old one. Utilities must publish their forms and process online and post hosting capacity per distribution transformer each quarter. The renewable energy certificate meter became voluntary, with an affidavit and waiver if you skip it.
- Source: GMA News and SolarQuarter, both 2 September 2025.
- 2 April 2026 Joint Memorandum Circular 001, Series of 2026
- Ten working days at the utility and three at the local government, with an application deemed approved if nobody acts. Temporary: it runs for the duration of the energy emergency declared under Executive Order 110, Series of 2026.
- Source: BusinessMirror, 2 April 2026.
How the application runs
The order is the same everywhere, because the rules set it: the system is designed and installed, the local government inspects it, the utility checks that its lines can take it, the agreement is signed, the meter is changed, and the system is switched on to export. What differs is the paperwork each utility asks for along the way. Meralco publishes its list, and since the 2025 Amended Rules every utility is required to.
What Meralco asks for, read 1 October 2026
- The application form
- Downloaded from the utility’s net metering page.
- Certificate of Final Electrical Inspection
- From your local government, after the installation has been inspected.
- A signed Net-Metering Agreement
- The contract between you and the utility.
- Certificate of Compliance
- Listed by Meralco as a requirement. The utility’s list does not say who issues it, so ask them.
- An application fee
- Set by the utility and printed on its own list.
One item depends on your installation. If you choose not to fit a renewable energy certificate meter, which the 2025 rules made optional, Meralco asks for a notarised affidavit and waiver and estimates your generation by the ERC’s method instead.
The distribution impact study
Before it connects you, the utility checks whether the local lines and the transformer that feeds your street can take what you will export. Meralco calls this a distribution impact study and says it looks for power quality problems, safety risks and system limits, and whether anything has to be upgraded first. The 2025 rules now require utilities to publish how much capacity each transformer has left, every quarter, which is the figure that study turns on.
If a cooperative bills you
The program is national and the cooperative has to run it, but two of the Pampanga utilities publish nothing about it, so the first step is a visit or a call to their office. The requirements page records what SFELAPCO, Angeles Electric, PELCO II and PELCO III each publish, which in two cases is nothing.
How long it takes
Since April 2026 the utility has ten working days from a complete application and the local government three, and an application nobody acts on in time is deemed approved. That is Joint Memorandum Circular 001 of 2026, from the Department of Energy, the Department of the Interior and Local Government and the Department of Public Works and Highways. The period it replaced was twenty working days.
Three things sit outside those clocks. The clocks start when the paperwork is complete, so a missing document resets them. The local inspection has to be scheduled and passed. And the meter change is a utility visit of its own. No utility in this list publishes a figure for the whole job from signing to switching on.
The circular is emergency legislation. It stays in force for the duration of the State of National Energy Emergency declared under Executive Order 110 of 2026, unless the DOE revokes it sooner. Reported by BusinessMirror on 2 April 2026.
What it means for a household day to day
While the sun is up, the house runs on the panels first and the surplus goes out. After dark, everything comes from the grid. The bill then shows what you imported, what you exported, and a credit for the export. The credit is the utility’s blended generation cost, which is one of several lines on a Philippine bill: transmission, distribution, system loss, subsidies and taxes are the others, and the credit does not cover them.
That one fact decides how to live with the system. A kilowatt-hour you use yourself in daylight displaces the whole rate. A kilowatt-hour you export earns the generation line and you buy the night’s power back at the whole rate. So the washing machine, the water pump and the aircon are cheaper to run at noon than at nine in the evening, and a system sized to what the house uses in daylight does the most for its size. Credits you do not use in a month now carry forward.
One more thing changes nothing: a brownout. A grid-tied system is required to disconnect when the line is dead, with or without net metering, so the lights go out with the street unless there is a battery and a backed-up circuit. Why that is, and which arrangement keeps the lights on.
Or no export at all
Net metering is only for a system that sends power out. A system set to export nothing, which Meralco calls Zero Export, needs no net metering agreement, and since Department Circular DC2026-08-0017 of August 2026, a utility cannot ask for pre-installation clearances or inspection fees. The trade is that any surplus is simply not generated. Which route suits a house depends on how much of its electricity it uses in daylight: net metering or zero export, and how to choose works it through, and the permits page sets the three routes side by side.
Net metering with your utility in Central Luzon
Net metering lets a customer with a renewable energy system send surplus power into the utility’s lines and get a credit for it. It runs under Republic Act 9513, the Renewable Energy Act of 2008, and under rules from the Energy Regulatory Commission. It is open to systems of up to 100 kW, and the forms and fees come from your own distribution utility, not from the installer.
Which utility is yours
The name is on your electric bill. For what each one publishes about net metering, see net metering requirements in the Philippines.
- SFELAPCO (San Fernando, Pampanga): what SFELAPCO publishes.
- Angeles Electric (Angeles, Pampanga): what Angeles Electric publishes.
- PELCO II (Pampanga): what PELCO II publishes.
- PELCO III (Pampanga): what PELCO III publishes.
- Meralco, for the Bulacan towns it supplies: Meralco’s net metering list.
- OEDC (Olongapo): OEDC’s six-step process.
- PENELCO (Bataan), provisional until confirmed on the ERC or DOE franchise list: requirements by utility.
- Tarlac Enterprises, Inc. (Tarlac City), TARELCO I and TARELCO II (other Tarlac towns), all provisional until confirmed on the ERC or DOE franchise list: requirements by utility.
How to apply, in order
- Read the utility’s name off your electric bill.
- Have the system designed and sized, with the installer’s documents for it.
- File the application with the utility, with the documents it lists.
- The utility checks that its lines can take the system and the local government inspects the installation.
- Sign the net metering agreement with the utility.
- The utility changes the meter, and the system is switched on to export.
Is net metering worth it?
It depends on how much of the power you use yourself in daylight. Take a house that uses 300 kWh in a month, with panels that make 350 kWh. If 200 kWh of that is used as it is made, the house buys 100 kWh from the grid and exports 150 kWh. The bill is for the 100 kWh, less a credit for 150 kWh at the utility’s generation cost. The 200 kWh used directly saved the whole rate, and the exported 150 kWh earns only the generation line.
Can I sell my excess solar power to the utility?
Not for cash under net metering. The exported kWh come off your bill as a credit at the utility’s blended generation cost, and credits you do not use carry forward to later bills.
How long does net metering take?
Since April 2026 the utility has ten working days from a complete application and the local government three. The inspection and the meter change come on top of those clocks. The section above, how long it takes, has the circular.
Do I need net metering if I do not export?
No. A system that never sends power out is a zero export system, covered in net metering or zero export. Whether a fee applies to a net metering application is set by your utility, and this page does not quote one.
For an installation, start at solar installation in Pampanga. We also install in Bulacan, Bataan, Tarlac and Olongapo.
What people ask about net metering
What is net metering in the Philippines?
It is the arrangement under which a household or business with a solar system of up to 100 kilowatts uses what it generates and sends any surplus into the distribution utility’s lines. The utility credits the surplus against the bill at its blended generation cost. The Department of Energy’s own primer describes it in those terms.
Who can apply for net metering?
A customer of a distribution utility with an account in good standing, with a renewable energy system of up to 100 kilowatts on their own premises. Meralco adds that the account must be in the applicant’s own name and have no unsettled balance when you apply.
How long does net metering approval take?
Under Joint Memorandum Circular 001 of 2026 the utility has ten working days from a complete application and the local government three, and an application nobody acts on inside those periods is deemed approved. Before April 2026 the utility period was twenty. The circular is tied to the energy emergency and lapses with it.
Those clocks run on complete paperwork. Getting the installation inspected and the meter changed is on top, and neither of those is promised by anyone on a calendar.
Is the credit worth the same as the electricity I buy?
No. The credit is the utility’s blended generation cost, which is one line of your bill. The rate you pay per kilowatt-hour also carries transmission, distribution, system loss, subsidies and taxes. So a kilowatt-hour you use yourself while the sun is up saves you more than one you export and buy back later.
Do unused credits expire?
Not any more. The one calendar year limit went with Department Circular DC2024-08-0025 in August 2024, and the 2025 Amended Rules confirm that credits bank and roll over against current and future billing periods.
Do I need net metering if I will not export anything?
No. Meralco calls that arrangement Zero Export and asks to be told about the system for safety reasons, and the August 2026 DOE circular on own-use solar bars a utility from asking for clearances or inspection fees before one is installed. Net metering is only for a system that will send power out.
Sizing a system that exports
With net metering the surplus is credited, so a system can be sized to the whole bill rather than to daylight use alone. The solar panel calculator does both sums from your monthly kilowatt-hours and shows the formula it used. A home installation that applies for net metering is part of our residential solar installation.
Paying for it is a separate question. GSIS members can borrow toward a home installation under the GSEL, and the application needs the installer’s quotation: the GSIS solar loan, its terms and who qualifies, with a dated note on where SSS stands.
Tell us who bills you
Send the name at the top of your bill and your monthly kilowatt-hours, and you will get a written answer on whether net metering or zero export suits the house, and what that utility will ask for.
Tell us the property and what you are trying to cut, and you will get a written answer with a size and a next step. No visit is booked and nothing is charged for asking.
Sources, read 8 October 2026 unless stated: Department of Energy, “The 5 Ws of Net-Metering”, Renewable Energy Management Bureau, September 2022; Cruz Marcelo and Tenefrancia, client note on Department Circular DC2024-08-0025 of 19 August 2024; GMA News and SolarQuarter, 2 September 2025, on ERC Resolution No. 15, Series of 2025; Meralco net metering FAQ, read 1 October 2026; BusinessMirror, 2 April 2026, on Joint Memorandum Circular 001, Series of 2026. This is a plain reading of what is published and it is not legal advice. Confirm the current position with your own distribution utility, or send us the details and ask us.