Solar panel cost in the Philippines: how to size it from your bill

The short answer: your monthly kilowatt-hours are the main input to the array size, and the quote follows that size. This page shows how to work the size out from your kilowatt-hours, and what a quotation has to itemise so you can compare two of them.

By Hamza Rivera, updated

Short answer: Published solar prices in the Philippines differ by about a factor of two between the cheapest and the dearest guide for the same size of system, and none of them has seen your roof. Solar is priced per roof, so the sizing tool works from your own kilowatt-hours and shows every assumption. Its result illustrates a size and does not quote a price.

This page works out the half of the arithmetic your own statement can settle, from figures you read off it, and lists the assumptions it used under the answer.

A supervisor in a white helmet checking a solar panel station with a laptop
Library photography, used to illustrate. Not a SolarPampanga installation.

Size it from your own bill

Take two figures off your latest statement. Everything below the line is an assumption you can change. The result illustrates a size; it does not quote a price.

From your statement

The rate is the total amount due divided by the kilowatt-hours billed. It is not the generation charge on its own. What the other charges on your bill are.

Add an appliance you are thinking of running

An air conditioner's rating is printed on the unit and on its manual. Use that number rather than its horsepower.

Assumptions, yours to change

What that comes to

Array you would need
1.4 kWp
Panels, at the size above
3
Roof it would occupy
7 m²
Electricity it would cover each month
180 kWh

Assumptions this used

Your 400 kWh a month. 45% of it used while the sun is up. 5.23 peak sun hours a day, the Global Solar Atlas figure at Pampanga (San Fernando), which is that point rather than an average of the province. A performance ratio of 0.8, covering inverter losses, heat, wiring and dust. 550 W panels at about 2.3 m² each. No electricity rate, until you put your own in.

Peak sun hours is the Global Solar Atlas value at one named point in each area, not an average of the province, and it follows the area you pick above. Type over it if you have a reading for your own address, and we will measure your roof properly before we quote anything.

Four things move the figure

Two quotations for the same house can differ honestly. These are usually why.

How much of your bill you want covered
Covering every kilowatt-hour you use is a much bigger array than covering the daytime ones.
The roof
Pitch, orientation, the material, how high it is and whether a truck can get near it all change the mounting and the labor. A low concrete deck and a two-storey GI roof behind a narrow gate are different jobs with the same panels on top.
The inverter, and whether a battery goes behind it
A string inverter feeding the grid is the cheapest arrangement. Microinverters, a hybrid inverter or any amount of storage all move the figure, and storage moves it most.
The paperwork
A grid-tied system applying for net metering carries an application, an inspection and a meter change. A zero-export system for your own use does not, and the 2026 DOE circular bars the utility from requiring a clearance, permit or inspection fee before it is installed.

What systems cost, by size

These are published figures, each with its source and date. Prices move with the peso, with panel and inverter prices and with labor, so each row is a dated figure and may be out of date by the time you read it. A site visit sets the final quote.

System Published range Source and date What the source says
3 kW ₱150,000 to ₱250,000 GroundWork.ph, solar cost guide, updated June 2026 Quick-guide figure. The guide does not say what the price includes.
3 kW ₱135,000 to ₱180,000 GroundWork.ph, same guide, updated June 2026 Grid-tied rate of ₱45,000 to ₱60,000 per kW, multiplied out.
5 kW ₱250,000 to ₱400,000 GroundWork.ph, same guide, updated June 2026 Quick-guide figure. The guide does not say what the price includes.
5 kW ₱225,000 to ₱300,000 GroundWork.ph, same guide, updated June 2026 Grid-tied rate of ₱45,000 to ₱60,000 per kW, multiplied out.
5 kW ₱300,000 Daily Guardian, 11 June 2026, quoting an Ember model ₱60 per watt, a modelling assumption that the article attributes to Ember.
Small kit ₱114,000 for 630 W Eco-Business, 16 November 2026 One retailer's starting price for a grid-tie kit. It works out to about ₱181,000 per kW. That is one kit, so it is not a rate for small systems. Outside the range above.

Our assumptions: grid-tied with no battery, and a house in Metro Manila or elsewhere on Luzon. The location is our assumption: the sources we used do not state one. Some sources do not say where their prices were gathered, so we have not assumed more than each source says.

Battery, hybrid and off-grid systems cost more. GroundWork's per-kW rates are ₱70,000 to ₱100,000 for hybrid and ₱100,000 to ₱150,000 for off-grid. The ₱60 per watt row above is the residential price in Ember's residential model, as the Daily Guardian article reports it, not a price we surveyed. Ember also estimates installed costs fell roughly 10% between May 2025 and May 2026 (Ember, 28 May 2026).

Sources: GroundWork.ph, "Solar Installation Cost Philippines", updated June 2026 (groundwork-ph.pages.dev). Daily Guardian, "Solar on your roof? You'll break even in 3 years", 11 June 2026 (dailyguardian.com.ph), which cites an Ember model at PHP 60 per watt residential. Eco-Business (Dialogue Earth), "The Philippines' 'solar surge' leaves many Filipinos behind", 16 November 2026 (eco-business.com).

The paperwork got lighter under the 2026 DOE circular

The Department of Energy issued Department Circular 2026-08-0017, which sets out simpler rules for own-use solar that exports nothing to the grid. Under it, a household installing a zero-export system that stays connected to the grid notifies its distribution utility, gets a building permit from the local government, and does not need a certificate of compliance from the Energy Regulatory Commission. An off-grid system notifies nobody, because there is no utility on the other end of it. A micro-solar system, as the circular defines it (plug-and-play, up to 1 kW of panels with an 800 W micro-inverter), needs neither the certificate nor the permit. The circular is on the DOE site.

Sources: Manila Bulletin, "DOE scraps permits, fees for home business solar panels", 6 August 2026 (mb.com.ph), and pv magazine, "Philippines eases rules for own-use solar systems", 11 August 2026 (pv-magazine.com). A Philstar column reports that some local governments have started charging for a solar "building permit". That is a report, not a rule we have checked, so ask your own local government before you budget around it. Check the current position with your distribution utility too.

Exporting, or not?

The connected or off-grid choice sets most of your paperwork, so settle it early.

Grid-tied, applying for net metering
Your surplus earns credits. There is an application to your utility, an inspection and a meter change.
Zero-export, own use only
Nothing goes back to the grid, so there is less to apply for.
Which permits each route actually needs What your own utility will ask for The solar panel calculator, with the formula shown Where the peak sun hours figure comes from What an appliance actually draws What your own roof changes about the job What a home installation involves

What to insist a quotation shows you

Whoever you hire, ours included. A single all-in figure with no breakdown is very hard to compare against anything.

WHAT A QUOTATION HAS TO SHOW Panel make, model, wattage and count Inverter make, model and type Mounting system and its fixings Labor, priced on its own Permit work, in or on top Warranty term, and whose One all-in figure, nothing to compare
Six lines. No amount appears here and none is implied: what is drawn is how many lines a quotation has to have before it can be set beside another one, which is what lets two prices be compared.

Questions we get about cost

How much is a solar panel installation in the Philippines?

Installed systems are priced per kilowatt of array, and the published ranges do not agree with each other for the same job. What actually sets your figure is how much of your bill you want covered, the roof it has to sit on, whether a battery goes behind the inverter, and which permits apply.

Work out the array size first, using the tool above and figures from your own statement. Then a quotation has something real to price.

How do I get a price for my roof?

Send us the town and your monthly kilowatt-hours and we will come and measure the rest. A price is worked out for one roof after a survey, so the figure you get is for that roof.

How many solar panels would run my air conditioner?

Take the watts printed on the unit’s own nameplate and multiply by the hours you run it in a day. Put that into the appliance row in the tool above and the array size goes up by the matching amount.

Running an air conditioner overnight is a different question, because that load falls when the panels are not producing. That one needs a battery, and it is worth asking us about separately.

Is solar worth it for my house?

It depends on three things you already know and one you probably do not. You know roughly what you use, what you pay per kilowatt-hour, and how long you plan to stay. The one to find out is how much of your usage falls in daylight, because that is the part an array without a battery can actually reach.

Can I pay for it in installments?

Ask us. Terms are agreed as part of the quotation, because they move with the size of the job and with whatever your bank or cooperative is offering that month. Government employees can also look at the GSIS solar loan for government employees.

Send us the two numbers and we will work from there

Your town and your monthly kilowatt-hours are enough for a first conversation. Everything after that needs somebody on the roof with a tape measure, which is the part a web page cannot do.

Ask for a quotation

Tell us the property and what you are trying to cut, and you will get a written answer with a size and a next step. No visit is booked and nothing is charged for asking.

Nothing on this page is a quotation. The sizing tool is an illustration built from figures you supply and assumptions you can change, and its output is not a promise about what any particular roof will generate or save. Send us the details or use the Message us button and we will talk about your actual property.

Ask for a quotation
Message us

Message us

Ask about your roof or your bill. It reaches a person, and we reply by email, WhatsApp or SMS.